Detailed timetable
09:19 London Bridge to Streatham Hill Shed
Wednesday 7 October 2026
Planned service information
- Power type
- Electric multiple unit
- Maximum speed
- 100 mph
- Operating characteristics
- D
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| London Bridge | 11 | 09:19 | 09:16 | -3 min | ||
| Abbey Street Junction | pass | 09:21 | 09:18 | -3 min | ||
| Spa Road Junction | pass | 09:21½ | 09:18½ | |||
| South Bermondsey Junction | pass | 09:22 | 09:19 | |||
| Old Kent Road Junction | pass | 09:24 | 09:23 | -1 min | ||
| Peckham Rye | 1 | pass | 09:29 | 09:27 | -2 min | |
| Tulse Hill | 4 | pass | 09:43½ | 09:41 | -2 min | |
| Leigham Junction | pass | 09:48½ | 09:46½ | |||
| Streatham Hill | 1 | 09:50 | 09:50 | 09:49 | 09:50 | On time |
| Streatham Hill Up Siding West | S1 | 09:54½ | 09:54½ | 09:54½ | 09:54½ | On time |
| Streatham Hill Signal 658 | 09:58½ | 10:03½ | 09:58½ | 10:03½ | ||
| Streatham Hill Up Siding West | S2 | 10:07½ | 10:07½ | 10:07½ | 10:07½ | |
| Streatham Hill Shed | S5 | 10:12 | 10:12 | |||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.