Service timetable
09:59 Wentloog (Freightliners) to London Gateway Frghtliner
Wednesday 7 October 2026
Planned service information
- Power type
- Diesel
- Timing load / planned train type
- 1475
- Maximum speed
- 75 mph
- Operating characteristics
- Y
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Wentloog (Freightliners) | 09:59 | 09:56 | -3 min | |||
| Pilning | 10:41½ | 10:51 | 10:38 | 10:50 | -1 min | |
| Swindon | UML | 11:45½ | 12:24 | 11:46 | 12:30 | +6 min |
| Reading | 15 | 13:19 | 13:22 | 13:18 | 13:21 | -1 min |
| Up Iver Loop | 13:55 | 14:02 | 13:55 | 14:02 | On time | |
| London Gateway Port Lg11 | 15:48 | 15:51 | 15:51 | 15:57 | +6 min | |
| London Gateway Arrival | 15:54 | 15:56 | 16:00 | 16:02 | +6 min | |
| London Gateway Frghtliner | 15:59 | 16:05 | +6 min | |||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.