Detailed timetable
23:44 Edinburgh to Tweedbank
Friday 9 October 2026
Planned service information
- Power type
- Diesel multiple unit
- Timing load / planned train type
- E
- Maximum speed
- 90 mph
- Train class code
- S
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Edinburgh | 1 | 23:44 | 23:43 | -1 min | ||
| Abbeyhill Junction | pass | 23:45½ | 23:45 | On time | ||
| Craigentinny Junction | pass | 23:47 | 23:47 | On time | ||
| Portobello Junction (Lothian) | 23:50 | 23:50½ | 23:50 | 23:49 | -1 min | |
| Brunstane | 23:54 | 23:54 | 23:51 | 23:53 | -1 min | |
| Newcraighall | 23:57 | 23:58 | 23:56 | 23:57 | -1 min | |
| Newcraighall South Junction | pass | 23:59 | 23:58 | -1 min | ||
| Shawfair | 00:02 | 00:02 | 00:00 | 00:02 | On time | |
| King's Gate Junction | pass | 00:03½ | 00:04 | +1 min | ||
| Eskbank | 00:05 | 00:06 | 00:05 | 00:06 | On time | |
| Newtongrange | 00:09 | 00:09 | 00:08½ | 00:09 | ||
| Gorebridge | 00:13 | 00:14 | 00:13 | 00:15 | +1 min | |
| Fushiebridge Junction | pass | 00:15 | 00:16 | +1 min | ||
| Tynehead Junction | pass | 00:21 | 00:21 | On time | ||
| Galabank Junction | pass | 00:30 | 00:30 | On time | ||
| Stow | 00:31 | 00:31 | 00:31 | 00:33 | +2 min | |
| Bowland Junction | pass | 00:35½ | 00:36 | +1 min | ||
| Galashiels | 00:39 | 00:40 | 00:40 | 00:41 | +1 min | |
| Tweedbank Sig Emb244 | pass | 00:43 | 00:44 | |||
| Tweedbank | 2 | 00:46 | 00:45 | On time | ||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.