Detailed timetable
10:37 Crewe to Appleby
Saturday 10 October 2026
Planned service information
- Power type
- Diesel
- Timing load / planned train type
- 455
- Maximum speed
- 95 mph
- Operating characteristics
- Q
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Crewe | UDL | 10:37 | ||||
| Crewe Coal Yard | pass | 10:41½ | ||||
| Winsford | pass | 10:47 | ||||
| Hartford Junction | pass | 10:51 | ||||
| Acton Bridge | pass | 10:53½ | ||||
| Weaver Junction | pass | 10:55 | ||||
| Acton Grange Junction | pass | 10:58 | ||||
| Warrington Bank Quay | 3 | pass | 10:59½ | |||
| Dallam Junction | pass | 11:00½ | ||||
| Winwick Junction | pass | 11:02½ | ||||
| Golborne Junction | pass | 11:04½ | ||||
| Springs Branch Junction | pass | 11:11 | ||||
| Wigan South Junction | pass | 11:12½ | ||||
| Wigan North Western | 5 | pass | 11:14 | |||
| Balshaw Lane | pass | 11:22 | ||||
| Euxton Junction | pass | 11:27 | ||||
| Farington Junction | pass | 11:33½ | ||||
| Lostock Hall Junction | pass | 11:43 | ||||
| Blackburn | 2 | pass | 11:56 | |||
| Daisyfield Junction | pass | 11:57 | ||||
| Langho | 2 | pass | 12:06 | |||
| Clitheroe | 2 | pass | 12:15 | |||
| Horrocksford Junction | pass | 12:15½ | ||||
| Hellifield | 2 | pass | 12:35 | |||
| Settle Junction | pass | 12:39½ | ||||
| Horton-in-Ribblesdale | 2 | pass | 12:49 | |||
| Ribblehead | 2 | pass | 12:55½ | |||
| Blea Moor | pass | 12:58 | ||||
| Garsdale | 1 | pass | 13:08½ | |||
| Kirkby Stephen | 2 | pass | 13:18½ | |||
| Appleby | 13:31 | |||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.