Detailed timetable
05:44 Peterborough North Yard GB Railfreight to Doncaster Up Decoy
Monday 12 October 2026
Planned service information
- Power type
- Diesel
- Timing load / planned train type
- 715
- Maximum speed
- 60 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Peterborough North Yard GB Railfreight | 05:44 | |||||
| New England Nth Junction | pass | 05:45½ | ||||
| Marholm Junction | pass | 05:47½ | 05:44 | -3 min | ||
| Helpston Junction | pass | 05:53 | 05:50 | -3 min | ||
| Tallington Junction | pass | 05:57 | 05:54 | -3 min | ||
| Stoke Junction | 06:18½ | 06:20 | 06:15½ | 06:12 | -8 min | |
| Grantham | GL | 06:30 | 06:48 | 06:22 | 06:42 | -6 min |
| Nottingham Branch Junction | pass | 06:50 | 06:45 | -5 min | ||
| Allington East Junction | pass | 06:54 | 06:50 | -4 min | ||
| Allington North Junction | pass | 06:55 | 06:50 | -5 min | ||
| Barkston East Junction | pass | 07:01 | 06:56 | |||
| Ancaster | pass | 07:07 | 07:02 | |||
| Rauceby | pass | 07:12 | 07:08 | -4 min | ||
| Sleaford | 3 | 07:18½ | 07:24 | 07:18 | 07:24 | On time |
| Sleaford North Junction | pass | 07:29 | 07:30 | +1 min | ||
| Metheringham | pass | 07:38½ | 07:42 | +4 min | ||
| Pelham Street Junction | pass | 07:49½ | 07:53½ | |||
| Lincoln Central | DM | 07:51 | 07:57½ | 07:55 | 08:01½ | +4 min |
| West Holmes Junction | pass | 08:00½ | 08:04½ | |||
| Pyewipe Junction | pass | 08:02 | 08:06 | |||
| Saxilby | pass | 08:07 | 08:11 | |||
| Gainsborough Lea Road | pass | 08:18½ | 08:22½ | |||
| Gainsborough Trent Jns | pass | 08:20 | 08:24 | |||
| Bessacarr Junction | pass | 08:38½ | 08:42½ | |||
| Black Carr Junction (Doncaster) | pass | 08:40½ | 08:44½ | |||
| Potteric Carr Junction | pass | 08:43 | 08:47 | |||
| Doncaster Up Decoy | 08:46 | 08:50 | ||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.