Detailed timetable
08:09 Severn Tunnel Ugl to Bristol High Level Siding
Monday 12 October 2026
Planned service information
- Power type
- Diesel multiple unit
- Timing load / planned train type
- E
- Maximum speed
- 90 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Severn Tunnel Ugl | 08:09 | 08:09 | On time | |||
| Severn Tunnel West | pass | 08:10½ | 08:10½ | |||
| Severn Tunnel East | pass | 08:14½ | 08:14½ | |||
| Pilning | 1 | pass | 08:15½ | 08:15½ | ||
| Patchway | 1 | pass | 08:19½ | 08:19½ | ||
| Filton Abbey Wood | 3 | 08:22 | 08:24 | 08:22 | 08:24 | |
| Horfield Junction | pass | 08:25½ | 08:25½ | |||
| Narroways Hill Junction | pass | 08:27 | 08:27 | |||
| Stapleton Road | 2 | 08:28½ | 08:31½ | 08:28½ | 08:31½ | |
| Dr Day's Junction | pass | 08:33 | 08:33 | |||
| Bristol East Junction | pass | 08:34 | 08:34 | |||
| Bristol Temple Meads | 3 | 08:35 | 08:47 | 08:35 | 08:47 | |
| Bristol East Junction | pass | 08:48 | 08:48 | |||
| Bristol Barton Hill W.r.d. | 08:52 | 08:56 | 08:52 | 08:56 | ||
| Bristol East Junction | pass | 09:00 | 09:00 | |||
| Bristol High Level Siding | 09:01 | 09:01 | ||||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.