Detailed timetable
05:30 Etches Park Sidings to Sheffield
Wednesday 14 October 2026
Planned service information
- Power type
- Diesel multiple unit
- Maximum speed
- 125 mph
| Location | Platform | Scheduled | Actual | |||
|---|---|---|---|---|---|---|
| Arrival | Departure | Arrival | Departure | Delay | ||
| Etches Park Sidings | 05:30 | 05:29 | -1 min | |||
| Derby | 05:32½ | 05:34½ | 05:30 | 05:32 | -2 min | |
| St.mary's South Junction | pass | 05:36 | 05:34 | -2 min | ||
| Ambergate Junction | pass | 05:41½ | 05:43 | +2 min | ||
| Clay Cross North Junction | pass | 05:51½ | 05:52 | +1 min | ||
| Chesterfield South Junction | pass | 05:54½ | 05:54 | On time | ||
| Chesterfield | 3 | pass | 05:56½ | 05:57 | +1 min | |
| Tapton Junction | pass | 05:57½ | No report | |||
| Barrow Hill North Junction | pass | 06:01½ | 06:02 | +1 min | ||
| Beighton Junction | pass | 06:07 | 06:10 | +3 min | ||
| Woodhouse Junction | pass | 06:10½ | 06:12 | +2 min | ||
| Woodburn Junction | pass | 06:15½ | 06:18 | +3 min | ||
| Nunnery Main Line Junction | pass | 06:17 | 06:21 | +4 min | ||
| Sheffield | 8 | 06:19 | 06:23 | +4 min | ||
Bold times are confirmed TRUST movement reports. Italic times are predictions based on the latest confirmed delay.